Assessing and deciding extension applications
87 Assessing and deciding extension applications
(1) When assessing an extension application, the assessment manager may
consider any matter that the assessment manager considers relevant, even if
the matter was not relevant to assessing the development application. Note—
For the assessment and deciding of an extension application for a development
approval that was a PDA development approval, see also the
Economic Development Act 2012 , section 51AL .
(2) The assessment manager
must, within 20 business days after receiving the extension application,
decide whether to— (a) give or refuse the extension sought; or
(b) extend
the currency period for a period that is different from the extension sought.
(3) The assessment manager and the applicant may agree to extend the 20
business day period.
(4) The assessment manager may decide the extension
application even if the development approval was given because of an order of
the P&E Court.
(5) The assessment manager must, within 5 business days after
deciding the extension application, give a decision notice to— (a) the
applicant; and
(b) any referral agency; and
(c) if the assessment manager
was a chosen assessment manager—the prescribed assessment manager; and
(d)
if the assessment manager is not a local government and the premises are in a
local government area—the local government whose local government area
includes the premises; and
(e) if the development approval was given or
changed because of an order of the P&E Court—the P&E Court; and
(f) if the
development approval was given or changed under a call in provision—the
Minister.
(6) If a decision notice is given to the P&E Court, the P&E Court
must attach the notice to the court’s file for the court’s order.
(7)
Despite section 85 , the development approval lapses— (a) if the extension
application is approved—at the end of the extended period; or
(b) if the
extension application is refused and the applicant does not appeal—when the
last of the following happens— (i) the day notice is given under subsection
(5) ;
(ii) the end of the currency period; or
(c) if the extension
application is refused, the applicant does appeal and the appeal is dismissed
or withdrawn—when the last of the following happens— (i) the day the
appeal is dismissed or withdrawn;
(ii) the end of the currency period; or
(d) if the extension application is refused, the applicant does appeal, and
the appeal is allowed—at the end of the extended period decided by the
court.
(8) If the applicant does appeal, the applicant may not start or carry
on development until the appeal is decided, unless allowed by an order of the
P&E Court.