PLANNING ACT 2016


- As at 2 August 2024 
- Act 25 of 2016 

TABLE OF PROVISIONS

           Long Title

CHAPTER 1 - PRELIMINARY

   1.      Short title
   2.      Commencement
   3.      Purpose of Act
   4.      System for achieving ecological sustainability
   5.      Advancing purpose of Act
   6.      Definitions
   7.      Act binds all persons

CHAPTER 2 - PLANNING

   PART 1 - INTRODUCTION

   8.      What are planning instruments
   9.      When planning instruments and designations have effect

   PART 2 - STATE PLANNING INSTRUMENTS

   10.     Making or amending State planning instruments
   11.     Minor amendments to State planning instruments
   12.     Making temporary State planning policies
   13.     Repealing State planning instruments
   14.     Advice to Minister about regional plans

   PART 3 - LOCAL PLANNING INSTRUMENTS

           Division 1 - Introduction

   15.     What part is about
   16.     Contents of local planning instruments
   17.     Minister’s guidelines and rules

           Division 2 - Making, amending or repealing local planning instruments

   18.     Making or amending planning schemes
   19.     Applying planning scheme in tidal areas
   20.     Amending planning schemes under Minister’s rules
   21.     Making or amending LGIPs
   22.     Making or amending planning scheme policies
   23.     Making or amending TLPIs
   24.     Repealing TLPIs or planning scheme policies
   25.     Reviewing planning schemes

           Division 3 - State powers for local planning instruments

   26.     Power of Minister to direct action be taken generally
   26A.    Power of Minister to direct particular amendment of planning schemes
   27.     Power of Minister to take urgent action
   28.     Limitation of liability

   PART 4 - SUPERSEDED PLANNING SCHEMES

           Division 1 - Applying superseded planning scheme

   29.     Request to apply superseded planning scheme
   29A.    When superseded planning scheme application for prohibited development may be made

           Division 2 - Compensation

   30.     When this division applies
   31.     Claiming compensation
   32.     Deciding compensation claim
   33.     Amount of compensation payable
   34.     Recording payment of compensation on title

   PART 5 - DESIGNATION OF PREMISES FOR DEVELOPMENT OF INFRASTRUCTURE

   35.     What is a designation
   36.     Criteria for making or amending designations
   37.     Process for making or amending designation
   38.     Process after making or amending designation
   39.     Duration of designation
   40.     Repealing designation—designator
   41.     Repealing designation—owner’s request
   42.     Noting designation in planning scheme
   42A.    Amending and repealing designations under old Act
   42B.    Process for making or amending guidelines under s 36 or the designation process rules

CHAPTER 3 - DEVELOPMENT ASSESSMENT

   PART 1 - TYPES OF DEVELOPMENT AND ASSESSMENT

           Division 1 - Instruments and categories

   43.     Categorising instruments
   44.     Categories of development
   45.     Categories of assessment
   46.     Exemption certificate for some assessable development

           Division 2 - Temporary accepted development

              Subdivision 1 - Declarations

   46A.    Regulation may declare temporary accepted development

              Subdivision 2 - Effect of declarations

   46B.    Application of subdivision
   46C.    Effect of declaration and carrying out material change of use
   46D.    Development applications during stated period
   46E.    Use of premises after stated period ends

   PART 2 - DEVELOPMENT APPLICATIONS

           Division 1 - Introduction

   47.     What part is about
   48.     Who is the assessment manager
   49.     What is a development approval, preliminary approval or development permit

           Division 2 - Making or changing applications

   50.     Right to make development applications
   51.     Making development applications
   52.     Changing or withdrawing development applications
   53.     Publicly notifying certain development applications

   PART 3 - ASSESSING AND DECIDING DEVELOPMENT APPLICATIONS

           Division 1 - Referral agency’s assessment

   54.     Copy of application to referral agency
   55.     Referral agency’s assessment
   56.     Referral agency’s response
   57.     Response before application
   58.     Effect of no response

           Division 2 - Assessment manager’s decision

   59.     What this division is about
   60.     Deciding development applications
   61.     Assessing and deciding variation requests
   62.     Complying with referral agency’s responses
   63.     Notice of decision
   64.     Deemed approval of applications

           Division 3 - Development conditions

   65.     Permitted development conditions
   65A.    Regulation about particular conditions
   66.     Prohibited development conditions
   67.     Agreements about development conditions

   PART 4 - DEVELOPMENT ASSESSMENT RULES

   68.     Development assessment rules
   69.     Amending the development assessment rules
   70.     Access to and evidence of the development assessment rules

   PART 5 - DEVELOPMENT APPROVALS

           Division 1 - Effect of development approval

   71.     When development approval has effect
   72.     When development may start
   73.     Attachment to the premises
   73A.    Development permits for building work given by private certifiers

           Division 2 - Changing development approvals

              Subdivision 1 - Changes during appeal period

   74.     What this subdivision is about
   75.     Making change representations
   76.     Deciding change representations

              Subdivision 2 - Changes after appeal period

   77.     What this subdivision is about
   78.     Making change application
   78A.    Responsible entity for change applications
   79.     Requirements for change applications
   80.     Notifying affected entities of change applications for minor changes
   81.     Assessing change applications for minor changes
   81A.    Deciding change applications for minor changes
   81B.    Withdrawing change applications for minor changes
   82.     Assessing and deciding change applications for other changes
   82A.    Additional referral agencies for change applications other than for minor changes

              Subdivision 3 - Notice of decision

   83.     Notice of decision

           Division 3 - Cancelling development approvals

   84.     Cancellation applications

           Division 4 - Lapsing of and extending development approvals

   85.     Lapsing of approval at end of currency period
   86.     Extension applications
   87.     Assessing and deciding extension applications
   87A.    Extension applications for development approvals given or changed under pt 6A
   88.     Lapsing of approval for failing to complete development

           Division 5 - Noting development approvals on planning scheme

   89.     Particular approvals to be noted

   PART 6 - MINISTER’S POWERS

           Division 1 - Introduction

   90.     What part applies to
   91.     Limit on Minister’s powers

           Division 2 - Minister’s directions

              Subdivision 1 - Directions generally

   92.     Minister not required to notify, consult or consider particular material
   93.     Directions generally

              Subdivision 2 - Directions to decision-makers

   94.     Directions to decision-makers—future applications
   95.     Directions to decision-makers—current applications
   96.     Directions about alternative assessment managers
   97.     Report about directions

              Subdivision 3 - Directions to referral agencies

   98.     What this subdivision is about
   99.     Directions to referral agency
   100.    Effect of direction

           Division 3 - Minister’s call in

   101.    What this division is about
   102.    Seeking representations about proposed call in
   103.    Call in notice
   104.    Effect of call in notice
   105.    Deciding called in application
   106.    Report about call ins

   PART 6A - DECLARING APPLICATIONS FOR STATE FACILITATED DEVELOPMENT

           Division 1 - Preliminary

   106A.   Application of part
   106B.   Definitions for part

           Division 2 - Making declarations

   106C.   Notice of proposed declaration
   106D.   Declaring applications for State facilitated development
   106E.   Notice of declaration
   106F.   Content of declaration notice
   106G.   Period of declaration
   106H.   Effect of declaration

           Division 3 - Assessing and deciding applications for State facilitated development

   106I.   Application of division
   106IA.  Notice about publicly notifying application
   106J.   Assessing and deciding application
   106K.   Obligations of decision-maker
   106L.   Notice of decision
   106M.   Publication of notice about decision

           Division 4 - Miscellaneous

   106N.   Reports about declarations and applications
   106P.   Matters for regulations
   106Q.   Delegations

   PART 7 - MISCELLANEOUS

   107.    Valid use or preservation covenants
   108.    Limitation of liability
   109.    Refunding or waiving fees

CHAPTER 4 - INFRASTRUCTURE

   PART 1 - INTRODUCTION

   110.    What chapter is about

   PART 2 - PROVISIONS FOR LOCAL GOVERNMENTS

           Division 1 - Preliminary

   111.    Application of part

           Division 2 - Charges for trunk infrastructure

              Subdivision 1 - Adopting charges

   112.    Regulation prescribing charges
   113.    Adopting charges by resolution

              Subdivision 2 - Charges resolutions

   114.    Contents—general
   115.    Provisions for participating local governments and distributor-retailers
   116.    Working out cost of infrastructure for offset or refund
   117.    Criteria for deciding conversion application
   118.    Steps after making charges resolution

              Subdivision 3 - Levying charges

   119.    When charge may be levied and recovered
   120.    Limitation of levied charge
   121.    Requirements for infrastructure charges notice

              Subdivision 4 - Payment

   122.    Payment triggers generally
   123.    Agreements about payment or provision instead of payment

              Subdivision 5 - Changing charges during appeal period

   124.    Application of this subdivision
   125.    Representations about infrastructure charges notice
   126.    Suspending appeal period by notice

           Division 3 - Development approval conditions about trunk infrastructure

              Subdivision 1 - Conditions for necessary trunk infrastructure

   127.    Application and operation of subdivision
   128.    Necessary infrastructure conditions
   129.    Offset or refund requirements

              Subdivision 2 - Conditions for extra trunk infrastructure costs

   130.    Imposing development conditions
   131.    Content of extra payment condition
   132.    Restriction if development completely in PIA
   133.    Extra payment conditions for development outside PIA
   134.    Refund if development in PIA
   135.    Refund if development approval stops
   136.    Extra payment condition does not affect other powers

              Subdivision 3 - Working out cost for required offset or refund

   137.    Process

           Division 4 - Miscellaneous provisions about trunk infrastructure

              Subdivision 1 - Conversion of particular non-trunk infrastructure before construction starts

   138.    Application of this subdivision
   139.    Application to convert infrastructure to trunk infrastructure
   140.    Deciding conversion application
   141.    Notice of decision
   142.    Effect of and action after conversion

              Subdivision 2 - Other provisions

   143.    Financial provisions
   144.    Levied charge taken to be rates

           Division 5 - Non-trunk infrastructure

   145.    Conditions local governments may impose

   PART 3 - PROVISIONS FOR STATE INFRASTRUCTURE PROVIDERS

   146.    Imposing conditions about infrastructure
   147.    Content of State-related condition
   148.    Refund if State-related condition stops
   149.    Reimbursement by local government for replacement infrastructure

   PART 4 - INFRASTRUCTURE AGREEMENTS

   150.    Infrastructure agreement
   151.    Obligation to negotiate in good faith
   152.    Content of infrastructure agreement
   153.    Copy of infrastructure agreement for local government
   154.    Copy of particular infrastructure agreements for distributor-retailers
   155.    When infrastructure agreement binds successors in title
   156.    Exercise of discretion unaffected by infrastructure agreement
   157.    Infrastructure agreement applies instead of approval and charges notice
   158.    Agreement for infrastructure partnerships

   PART 5 - MISCELLANEOUS

   159.    Particular local government land held on trust

CHAPTER 5 - OFFENCES AND ENFORCEMENT

   PART 1 - INTRODUCTION

   160.    What this chapter is about

   PART 2 - DEVELOPMENT OFFENCES

   161.    What part is about
   162.    Carrying out prohibited development
   163.    Carrying out assessable development without permit
   164.    Compliance with development approval
   165.    Unlawful use of premises
   166.    Exemptions if emergency causing safety concern

   PART 3 - ENFORCEMENT NOTICES

   167.    Show cause notices
   168.    Enforcement notices
   169.    Consulting private certifier about enforcement notice
   170.    Notifying about show cause and enforcement notices
   171.    Stay of enforcement notice
   172.    Application in response to show cause or enforcement notice
   173.    Enforcement authority may remedy contravention

   PART 4 - PROCEEDINGS FOR OFFENCES IN MAGISTRATES COURT

   173A.   Limitation on time for starting proceedings
   174.    Proceedings for offences
   175.    Proceedings brought in a representative capacity
   176.    Enforcement orders
   177.    Order for compensation
   178.    Order for investigation expenses
   179.    When fine is payable to local government

   PART 5 - ENFORCEMENT ORDERS IN P&E COURT

   180.    Enforcement orders
   181.    P&E Court’s powers about enforcement orders

   PART 6 - INSPECTORS

           Division 1 - Appointment

   182.    Appointment and qualifications
   183.    When appointment ends

           Division 2 - Identity cards

   184.    Issuing and returning identity card
   185.    Producing or displaying identity card

   PART 7 - ENTRY OF PLACES BY INSPECTORS

           Division 1 - Power to enter

   186.    General power to enter places

           Division 2 - Entry with consent

   187.    Application of this division
   188.    Incidental entry to ask for access
   189.    Matters inspector must tell occupier
   190.    Consent acknowledgement

           Division 3 - Entry with warrant

              Subdivision 1 - Issue of warrant

   191.    Application for warrant
   192.    Issue of warrant
   193.    Electronic application
   194.    Additional procedure for electronic application
   195.    Defect in relation to a warrant

              Subdivision 2 - Entry procedure

   196.    Entry procedure

           Division 4 - General powers of inspectors after entering places

   197.    Application of this division
   198.    General powers
   199.    Requiring reasonable help

   PART 8 - OTHER INSPECTORS’ POWERS AND RELATED MATTERS

           Division 1 - Stopping or moving vehicles

   200.    Application of division
   201.    Power to stop or move
   202.    Identification requirements if vehicle moving
   203.    Failure to comply with direction

           Division 2 - Seizure by inspectors and forfeiture

              Subdivision 1 - Power to seize

   204.    Seizing evidence at a place that may be entered without consent or warrant
   205.    Seizing evidence at a place entered with consent
   206.    Seizing evidence at a place entered with warrant
   207.    Seizing property subject to security
   208.    Securing seized thing

              Subdivision 2 - Safeguards for seized things

   209.    Receipt and decision notice for seized thing
   210.    Access to seized thing
   211.    Returning seized thing

              Subdivision 3 - Forfeiting seized things

   212.    Forfeiture by chief executive decision
   213.    Dealing with things forfeited or transferred to State

           Division 3 - Disposal orders

   214.    Disposal order

           Division 4 - Other information-obtaining powers of inspectors

   215.    Requiring name and address
   216.    Requiring documents to be produced
   217.    Requiring documents to be certified
   218.    Requiring information

           Division 5 - Damage

   219.    Duty to avoid inconvenience and minimise damage
   220.    Notice of damage

           Division 6 - Compensation for loss

   221.    Compensation for loss

           Division 7 - Other offences relating to inspectors

   222.    Obstructing inspector
   223.    Impersonating inspector

           Division 8 - Other provisions

   224.    Evidential immunity

   PART 9 - MISCELLANEOUS

   225.    Application of other Acts
   226.    False or misleading information
   227.    Executive officer must ensure corporation complies with Act
   228.    Responsibility for representative

CHAPTER 6 - DISPUTE RESOLUTION

   PART 1 - APPEAL RIGHTS

   229.    Appeals to tribunal or P&E Court
   230.    Notice of appeal
   231.    Non-appealable decisions and matters
   232.    Rules of the P&E Court

   PART 2 - DEVELOPMENT TRIBUNAL

           Division 1 - General

   233.    Appointment of referees
   234.    Referee with conflict of interest
   235.    Establishing development tribunal
   236.    Remuneration
   237.    Tribunal proceedings
   238.    Registrar and other officers

           Division 2 - Applications for declarations

   239.    Starting proceedings for declarations
   240.    Application for declaration about making of development application
   241.    Application for declaration about change to development approval

           Division 3 - Tribunal proceedings for appeals and declarations

   242.    Action when proceedings start
   243.    Chief executive excusing noncompliance
   244.    Ending tribunal proceedings or establishing new tribunal
   245.    Refunding fees
   246.    Further material for tribunal proceedings
   247.    Representation of Minister if State interest involved
   248.    Representation of parties at hearing
   249.    Conduct of tribunal proceedings
   250.    Tribunal directions or orders
   251.    Matters tribunal may consider
   252.    Deciding no jurisdiction for tribunal proceedings
   253.    Conduct of appeals
   254.    Deciding appeals to tribunal
   255.    Notice of tribunal’s decision
   256.    No costs orders
   257.    Recipient’s notice of compliance with direction or order
   258.    Tribunal may extend period to take action
   259.    Publication of tribunal decisions

CHAPTER 7 - MISCELLANEOUS

   PART 1 - EXISTING USES AND RIGHTS PROTECTED

   260.    Existing lawful uses, works and approvals
   261.    Implied and uncommenced right to use
   262.    Prospective categorising regulations unaffected

   PART 2 - TAKING OR PURCHASING LAND FOR PLANNING PURPOSES

           Division 1 - Taking or purchasing of land by local governments

   263.    When local governments may take or purchase land for planning purposes

           Division 2 - Taking of land by State

   263A.   When State may take land
   263B.   Power to take easements
   263C.   Vesting of land taken under s 263A
   263D.   Costs of taking land under s 263A
   263E.   Application of Acquisition Act, ss 36 and 37
   263F.   Notice of intention to dispose of land that is not required
   263G.   Power to dispose of land that is not required

   PART 3 - PUBLIC ACCESS TO DOCUMENTS

   264.    Public access to documents
   265.    Planning and development certificates

   PART 4 - URBAN ENCROACHMENT

   266.    Purpose of part
   267.    Making or renewing registrations
   268.    Amending conditions of, or cancelling, registrations
   268A.   Application to amend registration to include additional land in affected area
   268B.   Removal of land from affected area for registered premises
   268C.   Requirements for public consultation
   269.    Responsibilities of owners of registered premises relating to registration generally
   269A.   Responsibilities of owners of registered premises relating to amendments under s 268A
   270.    Responsibilities of owners of affected premises
   271.    Responsibilities on development applicants
   271A.   Requirements for notices given to registrar of titles
   272.    Rights of buyers in Milton rail precinct
   273.    Responsibilities of registrar of titles
   274.    Restriction on legal proceedings
   274A.   Provisions relating to new or amended authority for registered premises
   275.    Regulation may prescribe matters

   PART 4A - SERVICE OF DOCUMENTS

   275A.   Application of part
   275B.   Service of documents
   275C.   Certificate of service

   PART 4B - APPLICABLE EVENTS

           Division 1 - Preliminary

   275D.   Definitions for part

           Division 2 - Declaring applicable events

   275E.   Declarations of applicable events
   275F.   Extensions of applicable event periods
   275FA.  Minister may revoke declarations of applicable events

           Division 3 - Temporary use licences

              Subdivision 1 - Preliminary

   275G.   Application of division

              Subdivision 2 - Applications for temporary use licences

   275H.   Applications for temporary use licences
   275HA.  Chief executive may consult about applications
   275I.   Decisions on applications
   275J.   Notices of decisions
   275K.   Period of temporary use licences
   275L.   Effect of temporary use licences

              Subdivision 3 - Extension of temporary use licences by application

   275LA.  Application of subdivision
   275LB.  Applications to extend temporary use licences
   275LC.  Chief executive may consult about applications
   275LD.  Decisions on applications
   275LE.  Notices of decisions

              Subdivision 4 - Power of Minister to extend all temporary use licences

   275LF.  Minister may make declaration extending period of all temporary use licences

              Subdivision 5 - Amendment or cancellation of temporary use licences by application

   275LG.  Applications to amend temporary use licences
   275LH.  Chief executive may consult about applications
   275LI.  Decisions on applications
   275LJ.  Notices of decisions
   275LK.  Requests to cancel temporary use licences

              Subdivision 6 - Amendment, suspension or cancellation of temporary use licences by chief executive

   275LL.  Grounds for chief executive to amend, suspend or cancel temporary use licences
   275LM.  Chief executive may amend, suspend or cancel temporary use licences

              Subdivision 7 - Delegations

   275M.   Delegations

           Division 4 - Declaring uses and classes of uses

   275N.   Application of division
   275O.   Declarations of uses and classes of uses
   275P.   Effect of declarations under s 275O
   275PA.  Minister may extend period of declarations under s 275O
   275PB.  Minister may revoke declarations under s 275O

           Division 5 - Extending and suspending periods under Act

   275Q.   Application of division
   275R.   Extension of periods for doing things under Act
   275S.   Suspension of periods for doing things under Act

   PART 4C - PROVISIONS FOR SPRINGFIELD STRUCTURE PLAN

           Division 1 - Preliminary

   275T.   Definitions for part
   275U.   Relationship between this part and particular provisions

           Division 2 - Plan applications generally

   275V.   Who may make plan applications
   275W.   Restrictions on approving plan applications

           Division 3 - Non-SCG plan applications

   275X.   Requirements before making non-SCG plan applications
   275Y.   Requirements in relation to making and assessing non-SCG plan applications
   275Z.   SCG must give statements about particular matters
   275ZAA. Queensland Urban Utilities may make representations about non-SCG plan applications
   275ZA.  Local government must notify particular entities of decisions about non-SCG plan applications
   275ZAB. Application of Springfield structure plan, s 2.2.4.6

           Division 4 - Development in structure plan area

   275ZB.  Restrictions on starting development in structure plan area

           Division 5 - Dispute resolution

   275ZC.  Application of ch 3, pt 5, div 2, sdiv 1
   275ZD.  Particular appeal periods suspended
   275ZE.  Dispute notices under Springfield structure plan
   275ZF.  Entities entitled to receive dispute notices and join disputes
   275ZG.  Modification of particular provisions of Springfield structure plan relating to disputes
   275ZH.  Assessment manager may give new decision notice

   PART 4D - HERITAGE PLACES

   275ZI.  Restriction on impact assessment and conditions for particular applications
   275ZJ.  Assessment and decision rules for particular development involving State heritage places

   PART 5 - OTHER PROVISIONS

   276.    Party houses
   278.    Application of P&E Court Act evidentiary provisions
   279.    (Repealed)
   280.    References in Act to particular terms
   281.    Delegation
   282.    Approved forms
   283.    Guideline-making power
   284.    Regulation-making power

CHAPTER 8 - REPEAL, TRANSITIONAL AND VALIDATION PROVISIONS

   PART 1 - REPEAL PROVISION

   284A.   Act repealed

   PART 2 - TRANSITIONAL PROVISIONS FOR REPEAL OF SUSTAINABLE PLANNING ACT 2009

           Division 1 - Introduction

   285.    What this part is about

           Division 2 - General provisions

   286.    Documents
   287.    Statutory instruments
   288.    Applications generally
   289.    References to the old Act and the repealed Integrated Planning Act 1997
   290.    Lawful uses of premises
   291.    State planning regulatory and standard planning scheme provisions
   292.    Declaration for certain continued provisions

           Division 3 - Planning

   293.    Rules about amending local planning instrument consistent with Act
   294.    Amending State planning instrument consistent with Act
   295.    Request for application of superseded planning scheme
   296.    Compensation claims

           Division 4 - Development assessment

   297.    Categorising development under designations
   298.    Water infrastructure applications
   299.    Development approvals and compliance permits
   300.    Change applications for designated infrastructure

           Division 5 - Infrastructure

   301.    Infrastructure charges notices
   302.    Levied charges
   303.    Infrastructure charges
   304.    Infrastructure charges resolutions
   305.    Infrastructure charges in declared master plan area
   306.    Infrastructure conditions
   307.    Infrastructure conditions—change or extension approval
   307A.   Application to convert infrastructure to trunk infrastructure
   308.    Infrastructure agreements

           Division 6 - Enforcement and dispute resolution

   309.    Committee
   310.    Show cause notices and enforcement notices
   311.    Proceedings generally
   312.    Particular proceedings

           Division 7 - Miscellaneous

   313.    Keeping documents
   314.    Structure plans
   315.    Master plans
   316.    Development control plans
   317.    Rezoning approval conditions
   318.    Rezoning approval agreements
   319.    Compliance assessment of documents or works
   320.    Public housing development
   321.    LGP&E Act approvals
   322.    Milton XXXX Brewery
   323.    Transitional regulation-making power

   PART 3 - TRANSITIONAL AND SAVING PROVISIONS FOR WASTE REDUCTION AND RECYCLING AMENDMENT ACT 2017

   324.    Definitions for part
   325.    Responsible entity for particular existing change applications
   326.    Requirement for owner’s consent for particular existing change applications
   327.    Requirement for owner’s consent for particular existing extension applications
   328.    Existing appeals—excluded applications

   PART 4 - TRANSITIONAL PROVISIONS FOR VEGETATION MANAGEMENT AND OTHER LEGISLATION AMENDMENT ACT 2018

   329.    Definitions for part
   330.    Development applications made but not decided before commencement
   331.    Certain development approvals not affected
   332.    Unlawful clearing not an offence during interim period
   333.    Development application for certain operational works during interim period
   334.    Development application for certain material change of use during interim period

   PART 5 - TRANSITIONAL AND VALIDATION PROVISIONS FOR ECONOMIC DEVELOPMENT AND OTHER LEGISLATION AMENDMENT ACT 2019

   335.    Definitions for part
   336.    Particular existing decisions about superseded planning scheme requests
   337.    Existing superseded planning scheme applications
   338.    Particular planning changes
   339.    Particular existing applications
   340.    Particular representations dealt with before commencement
   341.    Conditions of existing development approvals
   342.    Lapsing of particular development approvals under old Act
   343.    Validation provision for particular development approvals
   344.    Validation provision for particular infrastructure charges notices under old Act
   345.    Particular existing appeals
   346.    Declaratory proceedings in P&E Court for particular matters under old Act
   347.    Appeals about particular decisions under old Act

   PART 6 - VALIDATION AND TRANSITIONAL PROVISIONS FOR PARTICULAR MATTERS

   348.    Validation of particular development approvals
   349.    Particular existing applications
   350.    Validation of particular operational work

   PART 7 - TRANSITIONAL PROVISION FOR IMPLEMENTATION OF THE SPIT MASTER PLAN ACT 2020

   351.    Application of s 31 in relation to particular adverse planning changes

   PART 8 - TRANSITIONAL PROVISIONS FOR FOREST WIND FARM DEVELOPMENT ACT 2020

   352.    Existing plan applications
   353.    Application of s 275ZC
   354.    Existing dispute notices

   PART 9 - TRANSITIONAL AND VALIDATION PROVISIONS FOR HOUSING AVAILABILITY AND AFFORDABILITY (PLANNING AND OTHER LEGISLATION AMENDMENT) ACT 2024

           Division 1 - Provisions commencing on assent

   355.    Transitional regulation-making power
   356.    Extension of validation under s 343 to referral agencies
   357.    Existing public notice periods continue

           Division 3 - Provisions for amendments relating to urban encroachment

   361.    Milton XXXX Brewery

   PART 10 - TRANSITIONAL PROVISIONS FOR CRIMINAL CODE (DECRIMINALISING SEX WORK) AND OTHER LEGISLATION AMENDMENT ACT 2024

   362.    Application of part
   363.    Definitions for part
   364.    Proceedings for particular offences if material change of use is accepted development on commencement
   365.    Proceedings for particular offences, and restricting use of information, if material change of use is assessable development on commencement
           SCHEDULE 1
           SCHEDULE 2