QUEENSLAND BUILDING AND CONSTRUCTION COMMISSION ACT 1991 - SECT 67I
Directions given under building contracts
67I Directions given under building contracts
(1) This section applies if under a building contract the contracting party
for the contract, or another person authorised under the contract, may,
without the agreement of the contracted party for the contract, give a
direction to the contracted party.
(2) Unless the building contract otherwise
provides, a direction may initially be given other than in writing.
(3)
However, if a direction is given other than in writing, the contracted
party— (a) may ask for the direction to be given in writing; and
(b) is not
required to comply with the direction until it is given in writing.
(4) If a
direction is given other than in writing, the contracting party commits an
offence if the direction is not given to the contracted party in writing
within 3 business days after it was given other than in writing.
Penalty— Maximum penalty—80 penalty units.
(5) In this section—
"direction" includes agreement, approval, authorisation, certificate,
decision, demand, determination, explanation, instruction, notice, order,
permission, rejection, request or requirement.