Statutory defects liability period
(1) This section applies to a building contract if— (a) under the
contract— (i) a retention amount may be withheld; or
(ii) a security may be
held after practical completion in relation to the need to correct defects in
the building work under the contract; and
(b) the contract does not provide
for the release of the retention amount or security at the end of an
identifiable period.
(2) The building contract is subject to a condition that
the retention amount or security must be released to the person entitled to it
at the end of 12 months starting on the day of practical completion for the
contract (the
"statutory defects liability period" ).