When work is taken to have started—Act, s 71F
43 When work is taken to have started—Act, s 71F
(1) For section 71F of the Act , residential construction work is taken to
start when— (a) if the work includes the erection or construction of a
footing system or slab or the provision of sewerage or drainage on a
site—the erection or construction of the footing system or slab, or the
provision of sewerage or drainage, physically starts on the site; or
(b)
otherwise—work for the renovation, alteration, extension, improvement or
repair of an existing building on a site physically starts on the site.
(2)
In this section—
"physically starts" , for residential construction work, does not include
starting any of the following— (a) the preparation of plans or
specifications for the performance of the work;
(b) design work;
(c)
administration services;
(d) earthmoving or excavating;
(e) site work
related to the residential construction work.