FOREST WIND FARM DEVELOPMENT ACT 2020 - SECT 15

Term of access licences

15 Term of access licences

(1) An access licence—
(a) takes effect on registration under section 25 ; and
(b) continues in effect until the earliest of the following days or events—
(i) the expiry day for the access licence stated in the relevant development agreement for the licence or, if a related project lease is renewed under section 46 , the end of the term of the renewed project lease;
(ii) the relevant development agreement for the access licence stops having effect;
(iii) the day that is 30 days after the holder of the access licence stops being the proponent for the relevant development agreement for the licence;
(iv) a related project lease stops having effect, other than because the lease is taken to have been surrendered under the Land Act 1994 , section 162 (6) ;
(v) the access licence is surrendered under section 20 ;
(vi) the access licence is cancelled under section 21 ;
(vii) 29 June 2109.
(2) However, an access licence does not stop having effect under subsection (1) (b) (iii) if, before the day mentioned in the subsection, the holder of the licence complies with section 27 (1) (a) in relation to a transfer of the licence.
(3) In this section—

"related project lease" , in relation to an access licence, means a project lease given in relation to the same development agreement as the access licence.