14—Amendment of section 36AC—Interpretation
Section 36AC—after its present contents (now to be designated as subsection (1)) insert:
(2) For the purposes of the definition of "excluded generator", if there are 2 or more meters for measuring the consumption of electricity on a site owned or occupied by 1 customer, in assessing the purpose of the installation of a generator on the site to determine whether or not the generator is an excluded generator, the operator of the distribution network must take into account the electricity consumption of the customer on the site as a whole (despite the fact that, for example, most or all of the electricity consumption on the site is recorded by a different meter from the meter to which the generator is connected).