(1) On completion by the Link corporation of any work of relocation or rectification of Utility infrastructure under Subdivision 5, the Utility must assess the work and—
(a) if it is satisfied that the work is satisfactory and complete, certify that fact to the Link corporation; or
(b) if it is not satisfied that the work is satisfactory or complete, notify the Link corporation that more work is required.
(2) The notice under subsection (1)(b) must specify as clearly as possible the work that is required.
(3) If the Utility does not give a certificate or notice under subsection (1) within 14 days after the Link corporation notifies it of the completion of the work, the Utility is deemed to be satisfied with the work.
(4) If the Utility gives a notice under subsection (1)(b), the Link corporation must complete the further work required in the notice within the period of 30 days after receipt of the notice or any longer period specified in the notice.
(5) This section does not apply if the Link corporation is unable to identify the Utility that owns or operates the Utility infrastructure.
S. 56X inserted by No. 81/2006 s. 72.