(1) A licensed
plumbing contractor who has given a notice of intention to carry out work
including a performance solution must, by giving notice to the Board in the
approved form, withdraw the notice of intention to the extent that the
contractor is not going to carry out the work including the performance
solution.
Penalty for this subregulation: a fine of
$3 000.
(2) A licensed
plumbing contractor must comply with regulation 45B in relation to work
including a performance solution that has been completed by the contractor
if —
(a) the
contractor has given a notice of intention to carry out the work; and
(b) the
contractor has commenced the work; and
(c) the
contractor is not going to complete all the work.
Penalty for this subregulation: a fine of
$3 000.
[Regulation 45C inserted: Gazette 24 Apr 2015
p. 1498‑9; amended: Gazette 29 Apr 2016 p. 1345;
13 Dec 2016 p. 5626‑7.]
[Heading inserted: Gazette 13 Dec 2016
p. 5628.]