(1) A person who
proposes to carry out Class 1 demolition work or Class 2 demolition work in a
manner that would be in accordance with AS 2601 must notify the regulator at
least 5 working days before the work is intended to begin.
(2) The notification
must be made in the manner and form approved by the regulator and must be
accompanied —
(a) by
written confirmation of the nominated supervisor that another person will not
be allowed to carry out the demolition work unless that person is a competent
person; and
(b) by
written confirmation of the person who holds a demolition licence —
(i)
that the demolition work will be directly supervised by a
competent person at all times when the demolition work is being carried out;
and
(ii)
of the name and qualifications or experience of the
person who will conduct the supervision.
(3)
Subregulation (4) applies to an emergency service organisation in
relation to demolition work carried out or proposed to be carried out by an
emergency service worker at the direction of the emergency service
organisation in responding to an emergency.
(4) An emergency
service organisation must give notice under subregulation (1) as soon as
practicable (whether before or after the work is carried out).