(1) A person who
proposes to carry out Class 1 demolition work or Class 2 demolition work but
to carry out the work in a manner that would not be in accordance with AS 2601
must, at least 10 working days before the work is intended to begin,
apply to the regulator for approval to carry out the work.
(2) The application
must be made in the manner and form approved by the regulator and must be
accompanied by —
(a) the
work plan referred to in AS 2601 in respect of the demolition work; and
(b) such
other information as the regulator requires to consider the application.