[Home]
[Databases]
[WorldLII]
[Search]
[Feedback]
Land and Environment Court of New South Wales |
Last Updated: 16 July 2002
NEW SOUTH WALES LAND AND ENVIRONMENT COURT
CITATION: Mosman Municipal
Council v Mitchelson [2002] NSWLEC 111
PARTIES:
PROSECUTOR
Mosman Municipal Council
DEFENDANT
Darren
Mitchelson
CASE NUMBER: 50068 of 2001
CATCH WORDS:
Prosecution
LEGISLATION CITED:
Crimes (Sentencing Procedure) Act
1999, s 10
Environmental Planning and Assessment Act 1979, s 125
Mosman
Local Environmental Plan 1998
CORAM: Cowdroy J
DATES OF HEARING:
30/05/02
DECISION DATE: 11/07/2002
LEGAL
REPRESENTATIVES
PROSECUTOR
Mr P Tomasetti
(Barrister)
SOLICITORS
Pike Pike Fenwick
DEFENDANT
Mr J
Robson (Barrister)
SOLICITORS
M E McMahon &
Associates
JUDGMENT:
IN THE LAND AND |
MATTER No. 50068 of 2001 |
Mosman Municipal Council
Prosecutor
v
Darren Mitchelson
Defendant
JUDGMENT
1. In these proceedings Mosman Municipal Council as prosecutor
(“the council”) charges Darren Mitchelson (“the
defendant”)
with an offence under s 125(1) of the Environmental Planning
and Assessment Act 1979 (“the EP&A Act”) in that he caused
development to be carried out contrary to a development consent (“the
offence”).
The offence arises out of the demolition of portions of the
exterior walls of a building known as Bradleys Head Private Hospital
(“the
building”) which, pursuant to the consent, were to be retained. The
development was located at 66 Bradleys Head
Road Mosman (“the
property”).
2. The defendant has entered a plea of guilty and has
agreed to pay the council’s costs of the proceedings. Accordingly the
Court is only required to determine penalty.
The Consent
3. An agreed statement of facts has been admitted into
evidence and supplemented by several affidavits. The council has not sought
to
challenge the evidence given by the defendant concerning the commission of the
offence.
4. By development application dated 4 April 2000 Waratah Village
Partners Pty Limited (“Waratah Village”) sought approval
of the
council for development of the property described as a “10 unit
retirement village conversion from Private Hospital” (“the
development”). Plans lodged with the development application showed that
several portions of the exterior walls
were to be retained. The application was
accompanied by an objection under State Environmental Planning Policy
(“SEPP”)
1 because the proposed maximum height of the development
did not comply with clause 13 of SEPP 5 (Housing for Older People or People
with
a Disability).
5. The council upheld the SEPP1 objection and development
consent was granted on 1 September 2000 (“the consent”) in respect
of “Alterations and additions to existing building for its conversion
to 10 dwellings for a residential care facility for older
people or people with
a disability” in accordance with the plans submitted with the
development application. Accordingly consent was not granted for the total
demolition
of the building.
Planning controls applicable to the property
6. The property is
within a heritage conservation area under the provisions of Mosman Local
Environmental Plan 1998 (“the Mosman
LEP”). Clauses 32 to 38 of the
Mosman LEP are relevant to development within heritage conservation areas.
Clauses 32 and
33 of the Mosman LEP as it existed at the time of the offence
relevantly provided:-
32 Heritage conservation objectives
(1) The objectives of
this Part are:
(a) to conserve the environmental heritage of the local
government area of Mosman, and
(b) to ensure that any development does
not adversely affect the heritage significance of heritage items and heritage
conservation
areas and their settings, and
...
33 Protection of heritage items and heritage conservation
areas
(1) The following development requires the Council’s
consent:
(a) demolishing, defacing, damaging or moving a heritage item
or a building, work, relic, tree or place within a heritage conservation
area,
or
(b) altering a heritage item or a building, work or relic within a
heritage conservation area by making structural changes to its
exterior,
or
(c) altering a heritage item or building, work or relic within a
heritage conservation area by making non-structural changes to the
detail,
fabric, finish or appearance of its exterior, except changes resulting from any
maintenance necessary for its ongoing protective
care which does not adversely
affect its heritage significance, or
...
(e) erecting a building on, or subdividing, land on which a
heritage item is located or which is within a heritage conservation
area.
At the time of the offence the property was listed as a heritage item under the provisions of the Mosman LEP.
The Offence
7. The defendant was contracted by a corporation known
as Equity & Law Pty Limited to oversee potential residential developments
in
the Sydney Metropolitan Area. One such project comprised the
development.
8. The defendant’s role as a project manager was to
supervise and organise the carrying out of works on the development. His
duties
included engaging sub-contractors, supervising work on the site, providing
access to staff and contractors, liaising with
Menai Excavations Pty Ltd
(“Menai Excavations”) and engaging them to carry out demolition
work.
9. Paul Gearing, a certifier from Inspec Pty Ltd was appointed
certifier for the project (“the certifier”). A construction
certificate for the development was issued on 20 December 2000 and following its
issue Menai Excavations commenced demolition works
on the property.
10. On
18 January 2001 whilst demolition was in progress the defendant contacted Mr
Charles Dalrymple of Taylor Thompson Whitting,
the engineer for the project
(“the engineer”) and requested him to assess the safety of the walls
and footings marked
for retention. The engineer duly conducted an inspection
and reported that such wall were not structurally sound.
11. Upon receipt
of such report the defendant then conferred with the certifier and sought his
consent to remove the unstable remaining
walls. In the mistaken belief that
such permission was given the defendant instructed Menai Excavations to demolish
the remaining
walls on the land. Such works were carried out between 10 and 30
January 2001.
Defendant’s evidence
12. The defendant testified that he met
the certifier on 23 January 2001 to discuss demolition of the walls and footings
which had
been found to be unsound by the engineer, and understood the certifier
gave him verbal approval for demolition of the walls and footings
because of
their instability. Believing that the certifier had authorised removal
of the remaining walls the defendant ordered their demolition.
Council’s Submissions
13. The council acknowledges that a
meeting took place between the defendant and the certifier. However the
certifier reported to
a council officer that he believed the defendant was
seeking approval for demolition of minor internal walls and not the external
walls of the building. The certifier was not called to give evidence to confirm
nor deny the defendant’s testimony and the
agreed statement of facts
neither confirms nor disputes the defendant’s evidence.
14. The council
does not challenge the defendant’s explanation. Nevertheless the council
submits the offence calls for conviction
and the imposition of a moderate fine.
The council points to the need for the penalty to operate as a general deterrent
to remind
developers of the need to observe strictly conditions forming part of
development consents as was considered in Canterbury City Council v Saad
[2001] NSWLEC 31; (2001) 112 LGERA 429 at 432.
Mitigation
15. Several factors establish that the defendant’s
conduct was not a deliberate attempt to circumvent the conditions forming
part
of the council’s consent but rather was an oversight arising from lack of
expertise and experience. The defendant had
not previously assumed the
responsibilities of a project manager, and he has acknowledged that the duties
he assumed in this new
capacity were beyond his capabilities and experience.
16. The Court takes into consideration additional matters advanced in
mitigation of penalty. The defendant did not stand to make
any financial gain
from the unauthorised demolition as he did not hold any equity in Waratah
Village nor personal interest in the
development. Secondly, only a small
portion of the total wall area of the building was to have been retained
pursuant to the consent.
It is estimated that the walls to retained amounted to
12.5% of the total external wall area of the building. Thirdly, the entire
building had been approved for demolition in a consent issued by council on 26
August 1999 which suggests that council, at least
at that date, considered that
the building was suitable for demolition.
17. The defendant has agreed to
pay the council’s costs in these proceedings amounting to $16,551.40. The
defendant also testified
to the exacting toll of this prosecution on his health
and family life. The defendant has no prior convictions. The defendant’s
income has been approximately $60,000 per year for the past three years and his
only cash asset consists of a share portfolio valued
at $10,000.
18. The
Court is prepared to accept that the defendant believed the advice given to him
by the certifier was to the effect that complete
demolition could take place.
The defendant entered a plea of guilty at an early stage in the proceedings and
thereby assisted the
prosecution of the charge. In addition the defendant has
shown considerable contrition and remorse for the consequences of his actions.
The utilitarian value of a plea of guilty will generally entitle a defendant to
a discount in penalty see Camilleri’s Stock Feeds Pty Ltd v Environment
Protection Authority (1993) 32 NSWLR 683; R v Thomson; R v Houlton
(2000) 49 NSWLR 383; Cameron v R [2002] HCA 6 (now reported in 187 ALR
65).
Section 10 Crimes (Sentencing Procedure) Act 1999
19. The parties
have agreed the offence is not “trivial” within the meaning of s 10
of the Crimes (Sentencing Procedure) Act 1999 accordingly no application under s
10 has been made. Nevertheless having regard to the various mitigating
circumstances the Court gives reasons why it would not appropriate
to apply s
10.
20. The fact an earlier consent had already been given for the demolition
of the whole building does not excuse the offence. In Cooper v Coffs Harbour
Council [1997] NSWSC 598; (1997) 97 LGERA 125 Howie AJ observed (at 143) that a breach of a
tree preservation order was a serious breach of a development approval and that
it
was immaterial that the council may have given the requisite consent.
21. By analogy such finding is applicable to the present circumstances where
the demolition of the building in toto may have been approved by council
had it been sought. The offence arises from failure of the defendant to
carryout the works without
approval. In Director-General of the Department
of Land and Water Conservation v Warroo (Lands) Pty Ltd [2002] NSWLEC 10,
Talbot J said:-
It is no answer that consent would have been forthcoming or that it was
likely to be granted. The law requires that an application
be made and
considered to enable the relevant assessments to be made in
advance.
22. The Court takes account of these principles but determines
that in the circumstances offence is one warranting the lowest range
of penalty.
Orders
23. The Court makes the following orders:-
1. The
defendant is convicted of the offence as charged.
2. The defendant is fined
$2000.
3. The defendant to pay the council’s costs of these
proceedings
4. Exhibits be returned.
AustLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.austlii.edu.au/au/cases/nsw/NSWLEC/2002/111.html