(1) The Treasurer must, at least once every 6 months, prepare a report about capital works for the Territory (a capital works report ).
(2) A capital works report must—
(a) include a progress report on the delivery of the capital works program for the Territory during the period since the previous capital works report; and
(b) include a statement of the expenditure on capital works for each directorate and territory authority for the financial year; and
(c) for each major capital works project—include—
(i) a statement of the expenditure on the project to date; and
(ii) a statement of the expenditure on the project for the financial year to date; and
(iii) a total budget for the project; and
(iv) an annual budget for the project.
(3) The Treasurer must—
(a) present a copy of each capital works report to the Legislative Assembly on the first sitting day after the report is prepared; and
(b) if the first sitting day is more than 60 days after the end of the period for which the report is prepared—give a copy of the report to each member of the Legislative Assembly within 60 days after the end of the period for which the report is prepared.
(4) A regulation may prescribe a major capital works project.
(5) In this section:
"capital works" includes works prescribed by regulation.
"expenditure" includes expenditure funded by capital injection or feasibility
expenditure funded by controlled recurrent payments.