Activities requiring 21 days notice
(1) A titleholder must notify the Regulator about any of the following well activities in the title area before starting the well activity:
(a) a well activity that involves drilling formation;
(b) a well activity that involves running tubular goods into a well or recovering tubular goods from a well;
(c) a well activity that involves removing a Christmas tree, tubing spool, casing spool or casing head from a well;
(d) a well activity that involves the installation of a Christmas tree saver for use with downhole operations or well testing.
(2) Notice of an activity mentioned in subregulation (1) must be given to the Regulator:
(a) at least 21 days before the start of the well activity; or
(b) if the Regulator agrees to a shorter period--at least the agreed number of days before the start of the well activity.
Activities requiring notice at any time before start of activity
(3) A titleholder must notify the Regulator about any of the following well activities in the title area before starting the well activity:
(a) a well activity, not mentioned in subregulation (1), that involves perforation or tubing punching;
(b) a well activity, not mentioned in subregulation (1), that involves installation, removal or locking open of a downhole safety valve, storm choke valve, gas - lift valve or injection valve;
(c) a well activity, not mentioned in subregulation (1), that involves the installation of a Christmas tree saver for use during maintenance work on Christmas tree components.
Form of notice
(4) Notice of a well activity must be in writing and must include the following information relating to the well activity:
(a) a reference that identifies the well operations management plan for the well;
(b) a description of the well, including the proposed or existing well name and number, the location of the well and the water depth;
(c) the name of the facility from which the well activity will be carried out;
(d) the name of the operator of the facility;
(e) a description of the well activity, including the objective, key elements, milestones and programmed depths;
(f) a list of any documents that have been prepared for the management, control or operation of the particular well activity;
(g) the timetable for carrying out and completing the activity.